Uranus Road, Revesby – culvert upgrade

We're upgrading the stormwater network to reduce the risk of flooding in the area. Anticipated completion April 2026, weather permitting.

In Construction

Where

View map
Uranus Road
West of the Shirley Street intersection
Revesby NSW 2211

How works may affect you

There will be a full road closure and traffic diversions in place. Fencing will barricade the work area and some access, pedestrian traffic and parking will be temporarily altered.

Traffic changes: Uranus Road, just west of Shirley Street intersection to Hydrae Street will be fully closed with detours in place. Heavy vehicles and more trucks will be passing through the area. Detour signage and traffic controllers will help motorists and pedestrians to move safely around the site.

Anticipated completion April 2026, weather permitting.
 
Council is upgrading the existing stormwater network beneath Uranus Road where it crosses Little Salt Pan Creek to accommodate heavy rainfall and reduce high-risk flooding in the area. 
 
Key elements of the project include:
  • Removal of existing large concrete pipes
  • Relocating a gas line
  • Re-alignment and rock armouring of constructed creek bank
  • Constructing a maintenance access track
  • Installing a new three-cell box culvert

When will works occur?

Construction will occur Monday to Friday between 7am-5pm and Saturday between 8am-4pm
 
Work started late-September 2025 and is expected to be complete by end - April 2026, weather permitting. 

Status

In Construction
Construction progress photos
excavation below the road and removal of pipes