Skip to main content
Bankstown CBD stormwater upgrade

The rapid growth of Bankstown CBD, driven by major commercial and transport developments (such as Western Sydney University, Sydney Metro and Bankstown Central shopping centre), means that our existing stormwater network needs to be upgraded

In Construction

Where

View map
The Appian Way & North Terrace
Bankstown NSW 2200

How works may affect you

Current works – Stage 3

The Mall will be closed from the corner of The Appian Way to the corner of Jacob Street. The Appian Way will be open to eastbound traffic only. The bus stop on The Mall will be temporarily relocated to the corner of Chapel Road and The Mall.

Pedestrians will still be able to cross The Mall at designated locations.

Status

In Construction
Overview of project
Our current stormwater network only has capacity for a one-in-five-year flood. Intense rainfall events cause high-risk flooding along The Appian Way and North Terrace, affecting properties, roads and pavements.
 
This project is designed to upgrade the stormwater network to accommodate a one-in-a-hundred-year flood event – a twenty-fold increase on current capacity. We will do this by increasing drainage capacity under the road surfaces of North Terrace, The Appian Way and The Mall, using pipes and culverts. 
 
The project will take place during 2024 and will last around 18 months. It will be carried out in stages to minimise impact on the community, but it will require road closures for a few months at a time, with diversions in place.  
 
This new stormwater network will futureproof Bankstown CBD from heavy rainfall events and pave the way for the Bankstown Complete Streets Project.
Plan of works

The work will be carried out in stages. Some stages will overlap and different roads will be closed for different periods. Traffic movement for the second stage of the project is shown on the map below.

Work will be carried out from Monday to Friday from 7am-5pm and some Saturdays between 8am and 4pm. Night works may be required at times between 8pm and 5am. 

StageCommencement date​Completion date
1Late January 2024November 2024
2November 2024May 2025
3May 2025July 2025
Stage 1
During most of Stage 1 (late January to November 2024), North Terrace was closed to traffic from the West Terrace underpass to the junction of the Appian Way. During this period, the North Terrace entrance/exit to Bankstown Central car park was not available. 
 
Stage 2

During most of Stage 2 (mid-November 2024 to early May 2025), there was excavation and installation of culverts, followed by surface works including paths and road resurfacing. 

The Appian Way was closed to traffic from North Terrace to The Mall. North Terrace was open between the West Terrace underpass and the train station. 

During this time there was reduced parking next to the work site.

Stage 3 – Current works

Stage 3 of the North Terrace/Appian Way Stormwater Culvert Upgrade will start at the corner of The Appian Way to the corner of Jacob Street. There will be excavation and installation of culverts, followed by surface works including paths and road resurfacing.

Stage 3 works will start in early May 2025 and the works are expected to be complete by July 2025, weather permitting.

The Mall will be closed from the corner of The Appian Way to the corner of Jacob Street. The Appian Way will be open to eastbound traffic only. The bus stop on The Mall will be temporarily relocated to the corner of Chapel Road and The Mall.

Pedestrians will still be able to cross The Mall at designated locations. Traffic controllers will be on site to help vehicles and pedestrians move safely through the area. There will be reduced parking next to the work site.

The temporary roundabout at the corner of Jacob St and The Mall will remain and continue to provide access to the car park in Bankstown Central.

Contact us
York Wang | Project Officer (02)97078175